Summarizing on the G702 and Adding Signatures: Transferring G703 Totals and Certifying the Payment Application

By Tammy Hoang, QuickBooks ProAdvisor — Construction Bookkeeping Specialist | Construction Cost Accounting
(949) 889-3283 | constructioncostaccounting.com

Direct answer: after the G703 is complete, its totals are carried onto the G702, the contractor signs the G702 before a notary, and the completed G703 is attached and submitted to the architect. Every figure on the G702 should trace back to the G703. The contractor certifies the application is accurate and the work conforms to the contract documents; the architect reviews, verifies the amounts, and either approves or adjusts them.
This guide covers how the G703 totals map onto the nine G702 summary lines, the arithmetic checks that catch errors before submission, a worked example, and the certification and signature sequence. It builds on CCA's guide to creating AIA invoices.
1. Transfer the G703 Totals to the G702

The G702 is the official summary and application for payment, so each of its figures should come from the G703 or follow from another G702 line. Procore's G702 guide numbers the summary lines and gives the arithmetic for several of them. Source: Procore, AIA G702.
G702 line | Summary item | Where it comes from |
1 | Original contract sum | The original contract amount; equals the G703 scheduled value total at the start |
2 | Net change by change orders | The change order summary |
3 | Contract sum to date | Line 1 plus line 2 |
4 | Total completed and stored to date | The G703 total completed and stored to date column |
5a, 5b | Retainage on completed work and on stored materials | The contract's retainage terms applied to each |
6 | Total earned less retainage | Line 4 minus line 5 |
7 | Less previous certificates for payment | The prior application's certified amounts |
8 | Current payment due | Line 6 minus line 7 |
9 | Balance to finish, including retainage | Contract sum to date minus line 6 |
Column letters matter here. In AIA's G703-1992 instructions, column G holds total completed and stored to date (D + E + F), column H holds the balance to finish (C − G), and column I is used for retainage only where variable retainage applies on a line-item basis; it can be left blank when constant retainage is withheld from the overall contract amount. Source: AIA G703-1992 instructions. Because forms and software exports can arrange columns differently, match each G702 line to the G703 column by its heading and not by its letter.
2. Double-Check the Math Before Anything Is Signed

CCA's guide is blunt: one wrong number can derail the application, and errors on the G702 can throw off the payment process. AIA's online workflow includes a pre-review step that ties the draft to supporting records and to the last approved application before anything is finalized. Source: AIA Contract Documents.
Assume a $600,000 original contract sum, $30,000 of net change orders, $250,000 of completed work and $20,000 of stored materials, 10% retainage on both, and $150,000 certified on earlier applications. The figures are illustrative arithmetic, not CCA client data.
G702 line | Item | Amount |
1 | Original contract sum | $600,000 |
2 | Net change by change orders | $30,000 |
3 | Contract sum to date (1 + 2) | $630,000 |
4 | Total completed and stored to date ($250,000 + $20,000) | $270,000 |
5a | Retainage on completed work (10% of $250,000) | $25,000 |
5b | Retainage on stored materials (10% of $20,000) | $2,000 |
6 | Total earned less retainage (4 − 5) | $243,000 |
7 | Less previous certificates for payment | $150,000 |
8 | Current payment due (6 − 7) | $93,000 |
9 | Balance to finish, including retainage (3 − 6) | $387,000 |
Three checks catch most errors: line 3 equals line 1 plus line 2, line 8 equals line 6 minus line 7, and the G703 total completed and stored ties to line 4. If any check fails, the application should be corrected before it is signed.
Want every G702 traced back to your G703 before you submit?
Construction Cost Accounting helps contractors prepare accurate payment applications with clean construction cost accounting.
constructioncostaccounting.com | (949) 889-3283
3. Add Certifications and Signatures

CCA's guide describes the sequence: the contractor completes and signs the G702, it is notarized, the completed G703 is attached, and the package goes to the architect, who reviews it for accuracy. Procore's guide says the standard form calls for notarization on every pay app and advises signing only in front of a notary unless both parties amend the contract. It also says the architect, project manager, or owner fills out the Certificate for Payment, so the contractor leaves that section blank. Source: Procore, AIA G702.
Who | What they do |
Contractor | Certifies the application is accurate and the work conforms to the contract documents; signs the G702 before a notary; attaches the completed G703 |
Architect | Reviews the package, verifies the amounts, and either certifies the requested amount or adjusts it and initials the changes |
Owner | Once the package is approved, makes payment directly to the contractor, unless the G702 specifies otherwise |
CCA's guide adds two warnings. Do not forge or skip signatures, because the application is a legal document. Check that names and addresses are correct before submitting, because payment goes to whoever is listed on the application. If the architect adjusts the amount, an explanation should be attached. CCA's guide to creating AIA invoices covers the supporting documents.
For construction accounting purposes, a construction bookkeeper should keep these records for every submitted application:
The G703 and G702 totals side by side, with each G702 line traced to its source
The signed and notarized G702 and the attached G703 as one package
The contractor and payee names and addresses exactly as listed on the application
The architect's certification, any initialed changes, and the attached explanation
Where Construction Cost Accounting Fits In

Construction Cost Accounting provides construction bookkeeping services for contractors who bill on G702 and G703 payment applications. Our construction bookkeeping services cover:
G703 schedule of values totals reconciled to every G702 line before submission
Retainage on completed work and on stored materials tracked by application
Signed packages, certifications, and architect explanations filed with each application
A construction bookkeeper who checks the arithmetic and the payee details each period
Learn more about our construction bookkeeping service.
Summarizing on the G702 means carrying the G703 totals onto the matching lines, checking the arithmetic, and signing before a notary. The contractor certifies accuracy, the architect verifies and either approves or adjusts with initials and an explanation, and the owner pays the contractor named on the form. Contractors whose applications move without rework are not relying on luck — their construction bookkeeping services trace every G702 line to the G703 and keep the signed package, supported by clean construction accounting and construction accounting records.