top of page

How Contractors Recover Overhead After a Delay: The Eichleay Formula for Unabsorbed Home Office Overhead (2026)

Writer: Cost Construction Accounting
Cost Construction Accounting
15 minutes ago
7 min read

By Tammy Hoang, QuickBooks ProAdvisor — Construction Bookkeeping Specialist | Construction Cost Accounting

(949) 889-3283  |  constructioncostaccounting.com

eichleay formula unabsorbed home office overhead

Direct answer: when a government-caused delay suspends your work, your overhead keeps running while the billings that would have absorbed it stop. On federal contracts, the Eichleay formula is the accepted way to recover that unabsorbed home office overhead: allocate overhead to the delayed contract by its share of total billings, convert it to a daily rate, and multiply by the days of compensable delay. It only works if you can prove standby and that you could not take on other work — and it depends on billing and overhead records that most contractors do not keep by contract period. Construction bookkeeping should keep them.

This guide covers what unabsorbed overhead is, the three-step calculation with a worked example, the conditions courts require, and what construction cost accounting must record to support a claim. It builds on the "How to Get Paid for Indirect Costs" section of CCA's construction overhead costs guide: an overhead rate recovers overhead on work performed, and the Eichleay formula addresses what happens when performance is suspended. This is general information, not legal advice — confirm current law and your contract's terms with construction counsel. Figures in the example are illustrative.

1. Why an Overhead Rate Stops Recovering Costs When Work Stops?

eichleay formula unabsorbed home office overhead

An overhead rate recovers indirect costs as direct work is billed. When a delay suspends the work, the office, administrative salaries, insurance, and other home office costs keep running while the billings that would have absorbed them stop. A federal technical report on Navy facilities contracting describes the result as unabsorbed overhead and notes that the per diem Eichleay method is the most frequently used way to price it (DTIC technical report). The formula takes its name from a 1960 decision of the Armed Services Board of Contract Appeals (Arnold & Porter).

THE EICHLEAY FORMULA, STEP BY STEP

As stated by the Federal Circuit in Wickham Contracting Co. v. Fischer

Step 1: allocable overhead

Multiply total overhead incurred during the contract period by the ratio of billings from the delayed contract to the contractor's total billings during that period

Step 2: daily rate

Divide the allocable overhead by the days of contract performance

Step 3: amount recoverable

Multiply the daily contract overhead rate by the number of days of compensable delay

What home office overhead includes

Extended home office overhead can include management and administrative salaries, rent, supplies, home office equipment, and insurance

Where it is the rule

On federal contracts, the Federal Circuit has held the Eichleay formula is the exclusive method for unabsorbed overhead caused by government delay, when its requirements are met

⚠  RED FLAG:  The Eichleay formula is a delay tool, not a change-order tool. Change orders in a contract generally do not produce Eichleay damages, while a delay that forces the contractor to stand by does (Arnold & Porter). Applying the formula to ordinary extra work, or to a private contract whose delay provisions say otherwise, invites a rejected claim.

2. A Worked Example: What a 40-Day Delay Can Mean?

eichleay formula unabsorbed home office overhead

Assume the delayed contract runs 300 days. During that period the contract bills $1,200,000, the contractor's total billings across all contracts are $4,800,000, and total overhead incurred is $600,000. A government-caused suspension then holds the contractor on standby for 40 days.

EICHLEAY CALCULATION, STEP BY STEP

Illustrative figures

Step 1: allocable overhead

$1,200,000 ÷ $4,800,000 = 25% of billings. 25% × $600,000 of overhead = $150,000 allocable to the contract

Step 2: daily rate

$150,000 ÷ 300 days of contract performance = $500 per day

Step 3: recoverable amount

$500 × 40 days of compensable delay = $20,000

What the claim still needs

Proof of standby, proof the contractor could not take on other work, and the billing and overhead records behind every number above

Source: Construction Cost Accounting illustration; method per Wickham Contracting Co. v. Fischer. Construction Cost Accounting | constructioncostaccounting.com

Two inputs drive the result: the contract's share of total billings and the overhead total for the period. Neither appears on a standard job cost report — they come from the general ledger and billing records, by period. A claim built on estimates or incomplete financial data is vulnerable: the Federal Circuit has noted that if the financial data is seriously incomplete, the Eichleay requirements are not met and the claim may simply be denied (Nicon, Inc. v. United States, 2003).

OWNER'S TAKEAWAY:  Close the books monthly with total billings by contract and total overhead by month. When a delay hits, the first two inputs to the formula should already be sitting in a report, not waiting to be reconstructed.

Could Your Books Support an Overhead Claim If a Delay Hit Tomorrow?

Many contractors cannot produce billings by contract and overhead by period without weeks of reconstruction. CCA builds bookkeeping that keeps both ready. In a free 30-minute review, we'll show you where your records stand.

constructioncostaccounting.com  |  (949) 889-3283 

3. What a Contractor Must Show? — and Why It Varies Outside the Federal System?

eichleay formula unabsorbed home office overhead

Courts have acknowledged two prerequisites to using the formula, assuming a compensable delay caused by the government: the contractor was on standby, and it was unable to take on other work (Nicon). Each one is a records question as much as a legal one.

WHAT THE CONTRACTOR MUST BE ABLE TO SHOW

Confirm current requirements with construction counsel

A compensable delay

A delay the government is responsible for and that is compensable — the starting point of the Federal Circuit's test

Standby

Performance on the contract was suspended or significantly interrupted, and the contractor had to be ready to resume immediately or on short notice

Unable to take on other work

The contractor could not replace the lost billings; continuing normal operations, including bidding on and performing additional contracts, does not by itself defeat a prima facie showing

Complete financial records

If the financial data is seriously incomplete, the requirements are not met and the claim may be denied

Outside federal contracts the picture changes. An Ohio appellate court held that the Eichleay formula is not the exclusive manner of determining unabsorbed home office overhead, in a case where the contractor used a variant called the HOOP formula (JD Supra). A California Court of Appeal decision reported in a January 2016 construction-law alert adopted the Eichleay formula along with the federal standby and unable-to-take-other-work requirements (LR Construction Law alert). Critics have also long argued the formula can misstate true overhead; a 1988 U.S. Department of Transportation report concluded it is subject to error and proposed alternatives (USDOT report).

Whatever the jurisdiction, the contract controls first. Define overhead, delay, suspension, and notice terms clearly before work starts, so recovery does not depend on a litigation formula. CCA's guides to pricing overhead into bids, the overhead recovery rate, and documenting and recovering back charges cover recovering costs on work performed and on remediation; the Eichleay formula covers the gap when performance stops.

An overhead rate recovers what work absorbs. The Eichleay formula is for the day the work stops and the overhead doesn't.

4. What to Track to Support an Unabsorbed Overhead Claim

Pulling this together, here is what a contractor should keep:

  • Billings by contract, by period — each contract's billings tied to the dates it ran, so the billing ratio can be computed

  • Total overhead by month — home office costs in separate accounts, so the contract-period total is a report, not a reconstruction

  • Days of performance and delay — start and finish dates, plus a dated log of every suspension, notice, and instruction to stand by

  • Standby and capacity evidence — records showing the crew and management stayed committed to resuming, and what other work was or was not available

  • Contract delay terms — suspension, delay, and notice provisions noted by job before work starts

 

With those in place, a contractor can calculate a delay claim from records instead of estimates, and knows before a delay hits whether the contract and the books support one. That is construction accounting doing its job on the overhead you cannot bill when the work stops.

Where Construction Cost Accounting Fits In?

eichleay formula unabsorbed home office overhead

Construction Cost Accounting provides construction bookkeeping services for contractors who want delay-related overhead claims backed by records. For this, that means:

  • Billings by contract and period — ready for the ratio the formula depends on

  • Home office overhead in clean accounts — monthly totals available without reconstruction

  • A dated delay and notice log — suspensions, instructions, and standby recorded as they happen

  • A construction bookkeeper who understands claim support — construction bookkeeping services built around evidence, not estimates

 

We work with contractors on federal and other long-term contracts who need their books to hold up when a delay turns into a claim. Our construction bookkeeper team — experienced in construction accounting for contract-based businesses — keeps billings, overhead, and delay records organized so the numbers are ready when counsel or a contracting officer asks. That is results-based construction bookkeeping for contractors who want to recover what a delay actually cost.

Get Delay-Claim-Ready Books

CCA builds construction bookkeeping around billings by contract, monthly overhead totals, and dated delay logs. Book a free 30-minute review and see where your books stand.

constructioncostaccounting.com  |  (949) 889-3283 

Unabsorbed home office overhead is the overhead that keeps running when a delay stops the billings meant to absorb it. On federal contracts, the Eichleay formula allocates overhead by billings share, converts it to a daily rate, and multiplies by the days of compensable delay — but only when the contractor proves standby and an inability to take on other work. Outside the federal system courts differ, so confirm the rules with construction counsel.

The contractors who recover overhead after a delay aren't reconstructing numbers after the fact — they're the ones whose construction bookkeeping services keep billings, overhead, and delay records current. For our full service, visit our construction bookkeeping page. CCA's construction bookkeeper team and construction accounting expertise give contractors that foundation. Good bookkeeping has the numbers ready before the delay arrives.

Comments


bottom of page