Allocating Equipment Costs to Jobs Without Double Counting: What FAR 31.105 Teaches Every Contractor (2026)

Writer: Cost Construction Accounting
Cost Construction Accounting
11 minutes ago
5 min read

By Tammy Hoang, QuickBooks ProAdvisor — Construction Bookkeeping Specialist | Construction Cost Accounting

(949) 889-3283  |  constructioncostaccounting.com

Direct answer: allocate owned-equipment costs to jobs through an equipment rate built from ownership costs (mainly depreciation) and operating costs (fuel, repairs, maintenance, tires) — and remove those same costs from your overhead pool so no dollar is double counted. The federal cost principles for construction contracts state this rule directly in FAR 31.105. Construction bookkeeping should keep equipment cost out of overhead once a job-level rate is charging it.

This guide covers the two parts of an equipment rate, the double-counting rule, and what construction cost accounting should track to make overhead allocation and equipment costs work together. The federal cost principles govern cost-based federal pricing — for private work they are a useful model, not a requirement.

1. Ownership Costs and Operating Costs Are Two Different Numbers

FAR 31.105 recognizes predetermined schedules of construction equipment use rates — including the U.S. Army Corps of Engineers' Construction Equipment Ownership and Operating Expense Schedule, industry-sponsored equipment cost guides, and commercially published schedules — that provide average ownership and operating rates. Ownership allowances should include depreciation; operating allowances may include fuel, filters, oil and grease, servicing, repairs and maintenance, and tire wear and repair. The Corps schedule is published as EP 1110-1-8.

WHAT AN EQUIPMENT RATE IS MADE OF

Ownership and operating costs behave differently and should be tracked separately

Ownership costs

Depreciation — and, under the federal rules, potentially facilities capital cost of money — fixed whether or not the machine runs

Operating costs

Fuel, filters, oil, grease, servicing, repairs, maintenance, tire wear and repair — costs that vary with hours of use

What schedules leave out

Labor, mobilization, demobilization, overhead, and profit are generally not reflected in equipment schedules and need separate consideration

Actual cost comes first

Under the federal rules, actual cost data must be used when it can be determined for each piece of equipment or group of similar equipment; schedules apply when it cannot

⚠  RED FLAG:  A schedule rate is an industry average, not your cost. If your records can support actual ownership and operating cost by machine, that is the stronger basis; a schedule is a fallback and a cross-check, not a substitute for tracking your own equipment costs.

2. The Double-Counting Rule

FAR 31.105 is explicit: when a schedule of predetermined use rates is used to determine direct costs, all costs included in the schedule's allowances must be identified and eliminated from the contractor's other direct and indirect costs charged to the contract. It adds that when the accounting system allocates site or home office overhead, the equipment costs may need to be included in the cost input base before the overhead rate is computed. That rule exists to prevent a double count.

The same logic applies to any contractor: if a job is charged an internal equipment rate covering depreciation, fuel, and repairs, those costs cannot also sit in the overhead pool spread across that job. CCA's guide to accurate job costing covers allocating equipment cost by actual hours, and the overhead allocation guide shows how pools are built.

OWNER'S TAKEAWAY:  The moment you start charging jobs an equipment rate, move equipment depreciation, fuel, and repairs out of your general overhead accounts. If they stay in both places, every job is charged for the same machine twice and your bids drift high.

Is Any Equipment Cost Counted Twice in Your Job Costing?

Many contractors charge jobs for equipment and also leave the same depreciation and repairs in overhead. CCA builds bookkeeping that keeps each dollar in one place. In a free 30-minute review, we'll show you where your accounts stand.

constructioncostaccounting.com  |  (949) 889-3283 

3. Machine Hours by Job Are the Data That Make the Rate Work

An equipment rate only allocates cost if you know how many hours each machine worked on each job. Track machine hours daily by job, divide each machine's or group's annual ownership and operating cost by its expected annual hours to build an internal hourly rate, and compare actual hours to the assumption each year. CPA guidance describes this as an internal rental rate approach, with the hourly rate developed from estimated annual equipment cost divided by estimated annual hours.

Construction cost accounting should also track idle time on its own, so the cost of an idle machine shows up as its own number instead of disappearing into job costs. The federal rules recognize the same idea: during work suspensions, the ownership allowance is limited to a standby amount.

A machine that sits idle still depreciates. The rate only works when the cost of idle time is visible instead of buried in the next job's bill.

4. What to Track So Equipment Is Charged Once, Correctly

Pulling this together, here is what a contractor should track:

  • Equipment cost by machine — ownership and operating costs tracked separately for each piece or group of similar equipment

  • Machine hours by job — logged daily and tied to the job cost code

  • Internal hourly rates — annual cost divided by expected hours, reviewed every year against actual hours

  • Overhead pool check — equipment costs removed from general overhead once a job-level rate charges them

 

With those in place, equipment cost lands on the jobs that used it, exactly once. That is construction accounting doing its job where overhead allocation and equipment meet.

Where Construction Cost Accounting Fits In

Construction Cost Accounting provides construction bookkeeping services for contractors who want equipment charged to jobs accurately. For this, that means:

  • Equipment cost tracked by machine — ownership and operating costs kept separate and current

  • Machine hours captured by job — the data an equipment rate depends on

  • Overhead pools checked for duplicates — so no equipment cost is counted in two places

  • A construction bookkeeper who understands equipment rates — construction bookkeeping services built around one charge per machine hour

 

We work with contractors who own equipment and want each job to carry its fair share of it. Our construction bookkeeper team — experienced in construction accounting for equipment-heavy contractors — keeps machine costs, hours, and overhead pools organized so nothing is charged twice. That is results-based construction bookkeeping for contractors who price equipment-driven work on real numbers.

Charge Equipment to Jobs Once, and Correctly

CCA builds construction bookkeeping around equipment rates, machine hours by job, and clean overhead pools. Book a free 30-minute review and see where your books stand.

constructioncostaccounting.com  |  (949) 889-3283 

Equipment cost allocation works when ownership costs and operating costs feed a job-level rate, machine hours are tracked by job, and the same costs are removed from the overhead pool. FAR 31.105 states the double counting rule plainly, and a double count is just as costly in private work. Track actual cost by machine, log hours daily, and confirm your pools don't repeat what the rate already charges.

The contractors who price equipment-driven jobs accurately aren't paying for the same machine twice in their own books — they're the ones whose construction bookkeeping services keep each dollar in one place. For our full service, visit our construction bookkeeping page. CCA's construction bookkeeper team and construction accounting expertise give contractors that foundation. Good bookkeeping charges every machine hour once.